• Strip out and refurbishment of 3 general learning areas and existing offices were converted into a general learning area and team laboratory.
  • Major trades included a vast amount of joinery, wall cladding and plasterboard ceiling in GLA 3 and the team lab.
  • Major challenges that we overcame through good design initiatives was the MVAC system. Also we had very limited time to set up this project and the program was very tight. Our team of experts worked together beautifully to deliver this project for the University on time and on budget.
  • The redesign and refurbishment of this space now means that students can attend University during COVID-19, whilst maintaining social distancing.

Project details
  • Education Client:
  • $600KProject Value:
  • 7 weeksDuration: