Finishing this fit‐out by deadline was truly a race against the clock.
The project’s main focus was to replace all existing refrigeration, however no contractor was
made available until three weeks in. It then wasn't until the sixth week that the casings could be
delivered.
But still, Streetbuild helped modernise the store in time, including all‐new shop‐fitting, deli,
seafood, meat & pizza sections and a minor adjustment to the bakery.
That resulted in an extension of trading floor space, plus a fresh coat of paint now has the store
looking better than ever.

Project details
  • Woolworths Client:
  • $1.1millionProject Value:
  • 10 weeksDuration: